Emerald Drive

Roadwork will require partial closures. Thank you for your patience!


As part of the Town’s annual investment in preventative maintenance, Emerald Drive is being reconstructed. Crews will remove the existing concrete and replace it with asphalt. Work is expected to start Monday, April 10, and wrap up by the end of July. 

Access is our priority


Maintaining access to residential areas is a priority for the Town, so the reconstruction will take place in sections. In an effort to complete this work safely and efficiently, one section at a time will be closed to through traffic. 

Current detours


Crews are expected to move to the fourth section of this project, between Kahala Circle and Diamond Head Drive on Thursday, June 14. Scroll down for a detour map. Thank you for your patience as we work to improve roads in our Town!

Overall plan


This project is expected to last through July. View below a map of how the work is expected to progress. 
Emerald_Schedule_Phase_4
Emerald_Schedule_All_Phases_5_30_2017

Annual pavement maintenance 


This roadwork is part of the Town’s annual Pavement Maintenance Program. This Council-approved program concentrates residential road maintenance to one of five defined residential areas each year on a rotating basis. The goal is to increase efficiency, reduce costs and minimize disruption to neighborhoods. 

Overall, the maintenance extends the life of Town roads and helps get the most out of the Town’s investment in infrastructure.